Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Pramono Flags Off 10,000 Runners at Soekarno Run 2026

    access_time15-02-2026 remove_red_eye1044 personFolmer
  2. Pramono Calls on Residents to Maintain Peace and Harmony During Ramadan

    access_time14-02-2026 remove_red_eye975 personFakhrizal Fakhri
  3. Jakarta Unveils Indonesia’s First SDGs Corner at Maritime Museum

    access_time15-02-2026 remove_red_eye927 personNurito
  4. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye897 personAldi Geri Lumban Tobing
  5. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye847 personAldi Geri Lumban Tobing