Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye829 personDessy Suciati
  2. Pasar Baru Festival 2026 Brings Historic District to Life

    access_time27-11-2026 remove_red_eye602 personFolmer
  3. Pramono Explores Collaboration with UNSW Sydney to Prepare Jakarta Scholarships

    access_time28-11-2026 remove_red_eye530 personDessy Suciati
  4. Jakarta Tops Teqball at 2026 PON Beach Games

    access_time27-11-2026 remove_red_eye518 personAldi Geri Lumban Tobing
  5. Jakarta Design Connect 2026 Showcases 50 Works by Artists and Designers

    access_time27-11-2026 remove_red_eye498 personAnita Karyati